FPP Carry Out A Chiller Pack Replacement At A Sensitive Data Centre In Tankersley
The task of removing and replacing 2 chiller packs each weighing 8,000kg was the order of the day at a sensitive HSBC Data centre.
The plant room is located in the basement of the data centre and accessed via a ramped access gangway and to add a further challenge the gangway floor is finished in ceramic tiles.
Working for our client Dornan Engineering Services one of our lift and shift teams with jacking and skating equipment were engaged on this operation.
Polyethylene ‘Track Mats’ were firstly installed to act as tile protection.
Each chiller was then negotiated up and down the ramp utilising anchored tirfor winches to act as motive force and load control for each chiller on the ramp.
To complete the service the offloading and loading of each chiller pack was undertaken utilising one of our hiab crane mounted vehicles.
Recent Articles
During a recent project aimed at upgrading the Boiler house at the Mondelez Marlbrook site, Factory Plant Projects executed a comprehensive turnkey removal and installation operation.FPP’s approach entailed a strategic…
Read MoreFPP has successfully executed projects for numerous microbreweries across the United Kingdom. Our track record demonstrates our proficiency in operating within constricted access areas while maintaining a steadfast commitment to…
Read MoreFactory Plant Projects executed a plant room tank installation on a bustling construction site in Leeds. Collaborating closely with the principal contractor and our client, FPP adeptly orchestrated the seamless…
Read MoreIn collaboration with a highly esteemed and long-standing customer, FPP successfully executed the installation of the new De-Alc plant at Camerons Brewery. This project constituted a pivotal component within a…
Read MoreFPP was contracted to conduct the lifting operations for a state-of-the-art precious metal recycling facility. Leveraging the capabilities of the electric pick & carry crane, FPP executed a diverse range…
Read MoreFPP was selected as the designated contractor entrusted with carrying out the intricate task of a staged relocation of our client’s equipment, all while sustaining uninterrupted operational continuity. In the…
Read More